The track re surface is scheduled to take place straight after our race meeting on Sunday February 19. This will disrupt the availability of the track for a few weeks and we will need some help from our members to try to make this happen in the most efficient and economical way.

Below is a timetable and the work needed to be done in each period, if you are able to help with any of these tasks of can organise someone to do a job please let me know. All jobs will have to be done within the timeframes listed to minimise downtime at the track . I am in the process of organising contractors to do the kerbs etc but if we can avoid having to pay commercial rates for some of these thing the club will be in a much better place.

The re surface will cover the complete race track (not the cut through), the entrance to the in grid (about 10 metres short of tyre barrier), all of the out grid (everything under the roof) and the side of the out grid (canteen side that is currently gravel)

Sunday February 19 Round 1 CDKC Club Championship and DD2 Series

  • Straight after race meeting
  1. Pull down start lights across track (Help needed)
  2. Level and prepare canteen side of out grid for surfacing ( Help Needed)
  • Monday February 20 – Monday February 27
  1. All ripple strips on outside of kerbs need to be removed, excavator required (If you can save the club $$$ please help)
  2. New concrete ripple strips to CIK spec installed on outside of track where required. Aprox 400 lineal metres (If you can save the club $$$ please help)
  • Tuesday February 28 to Friday March 3
  1. Track re surface (Organised)
  • After March 3
  1. Line making and painting ripple strips and curbs, Inner and outer track boundary’s marked, start line, finish line, no mans land, formation line, baulk line, grid markings on out grid and grid makings on track for standing starts. (If you can save the club $$$ please help)
  2. Ripple strips will need to set for 2 weeks before painting. (If you can save the club $$$ please help)
  3. Re contour run offs and gravel traps (Help Needed)
  4. General tidy up (Help Needed)
  • March 25 Track to re open for use (dependant on all the above going to plan)
  • Sunday April 2 Cols Castle Cup and Round 2 CDKC Club Championship